Sharmai Dir-150 MW, Shushai-Zhendoli Chitral -144 MW, Shogosin Chitral -132 MW

2014-12-23

Approved by ECNEC on Dec 31, 2013.
----------------------------------------------
PPP mode
----------------------------------------------
TOR for hiring of consultant was discussed in DCSC meeting dated 20-3-2014.
----------------------------------------------
Energy Apex Committee meeting was held on 2/6/2014. As per decision of the Committee these projects will be carried out in private Sector.
----------------------------------------------
It has been decided by Energy Apex Committee that all the three project will be constructed through private sector.
----------------------------------------------
The Bids have been floated in the press